The ground under construction can process about million tons of domestic sewage a year
VLADIVOSTOK, April 23, vladivostoktimes.com The construction of the solid domestic waste processing complex is going according to the schedule, as the Primorsky Territory Administration press service reported to RIA PrimaMedia. The constructors plan to finish it even before the stipulated date – in the fourth quarter of 2010.
As “Vostokstroyservice”, the primary contractor, reported, 219 people and 94 units of building machinery are involved in the construction.
Today they are dumping the main border levee and building the detour road around the ground. At the same time they are preparing a ditch and have already processed over 165 thousand cubic meter of ground coat.
The constructors plan to finish it even before the stipulated date – in the fourth quarter of 2010. For it they apply new technologies for it. We would remind you that the construction of the new modern solid domestic waste processing complex is being realized in the framework of the preparation for APEC Summit 2012.
“Vladivostok is developing. Our goal is to make it the city of the 21st century – comfortable, beautiful and safe, including ecologically safe. It means that Vladivostok needs modern reclamation technologies” says the Primorsky Territory Governor Sergey DARKIN.
The ground under construction can process about million tons of domestic sewage a year. Modern reclamation technologies will provide protection for the air, the surrounding area, and the water.